Due to the great void to be overcome, the option to implement a pre-molded box culvert had to be replaced by the execution at the site, witch changed the entire project concept, launching new construction challenges. For such, the project became a bridge with a deep foundation.
Construction of box culverts (bridges) over Córrego Itanguá
SAAE Sorocaba
6 months
R$ 755.957,40
• Total extension: 25,80m • Width: 13,00m • Form area: 1.314,50m² • Steal: 36.141kg • Concrete: 402,46m³ • Continuous Helical Displacement (CHD) Pile D=40cm – 40T = 322,00 m
Transportation