Since this was a large developing region – the eastside of São José dos Campos (SP) –we performed the full integration of the sewage system with this project, with characteristics such as the distances and logistics to execute the project and overcome natural barriers, as well as the implementation of the collectors going through several properties, which required permits. In the pumping stations, the main characteristic was the installation of Nemo positive-displacement pumps, facilitating the maintenance and operation of the stations.
Execution of Sanitation Sewage System Works for the Municipality of São José dos Campos (SP). Complementary works: Pararangaba Sub Watershed, including household connections, collection networks, trunk collectors, sewage pumping stations and sewage pumping lines. Southeast Development Coordination – REV and the Vale do Paraíba Business Unit – RV
Sabesp
01/08/2013 to 10/19/2016 (3 years and 9 months)
R$ 28.541.191,67
• Trunk collectors with diameters ranging from 200 mm to 400 mm: 19.978,25 m • Sewage pumping lines with diameters ranging from 100 mm to 300 mm: 7.707,50 m • Sewage collection network with diameters ranging from 150 mm to 200 mm: 26.148,55 m • Connection of households to the sewage network: 1.728,00 un • SPS Diamante: flow: 12.00 l/s; power: 10 cv • SPS Capão Grosso: flow: 35,00 l/s; power: 50 cv • SPS Majestic 1.1: flow: 9.00 l/s; power: 10 cv • SPS Majestic 1.2: flow: 14.50 l/s; power: 20 cv • SPS Majestic 1.3: flow: 18.00 l/s; power: 25 cv • SPS Vista Verde: flow: 76.40 l/s; power: 100 cv • SPS Alambari: flow: 54.50 l/s; power: 75 cv
Sanitation