The main aspect of this project was the large number of workers and equipment to meet the short deadline established. Several technical solutions were adopted to execute the sub-foundation reinforcement and yard drainage.
Execution of infrastructure works for the expansion of mill 3 and truck yard, Pindamonhangaba plant
Gerdau
05/15/2011 to 12/31/2011 (7 months)
R$ 12.200.000,00
• Cut and fill volume: 147,000.00 m³ • Box culvert 2.50 m x 1.50 m: 360.00 m • Rainwater gallery: diameter: between 400 mm and 1,000 mm; total extension: 7,284.00 m • Asphalt pavement: 12,437.00 m²
Earthworks